The History of I-270 in Colorado

Length: 5.35 (I-25/US 36 to I-70)
Exits: 6
Counties: 2 (Adams and Denver )
Cities: 2 (Commerce City and Denver)
Start of Construction: 1965
End of Construction: 1970
Initial Construction Costs: $8.9 million

National Impact
Construction Timeline
CDOT Personnel

50th Anniversary Main Page
Interstate 25
Interstate 70
Interstate 76
Interstate 225
Interstate 270
Colo. Interstate Fun Facts
Contact Us

National Impact

Use to benefit travel to and from Stapleton International Airport .

Construction Timeline

I-270 started being built in the late 1960s. The section from I-70 to Vasquez opened by 1968, and it opened up to I-76 by 1970. As originally built, I-270 started at a trumpet interchange on I-76 just east of I-25. Two lanes from eastbound I-76 blended off and become I-270, while from I-270 the two lanes merged onto westbound I-76, but those immediately became the exit lanes for northbound I-25 and westbound US 36.

Westbound US 36 connection history: In September 1999, the connection from WB I-270 to NB I-25 opened. If you wanted US 36, you still had to take the former route that mainline I-270 took west onto I-76. Then in mid-February 2000, the full westbound connection finally opened. Also opening was an exit from WB I-270 to Broadway. At the same time, several other things happened: A new exit from I-76 westbound to I-270 westbound opened, and the preexisting exit from westbound I-76 to NB I-25 and WB US 36 closed. Also the ramp from WB US 36 to Broadway closed, replaced by a new exit from NB I-25 to 70th Avenue .

As for the eastbound connection, the full connection from US 36 to EB I-270 opened August 16, 2003. No other ramp openings or closings happened with that, though.

December 12, 1965 Construction of I-270 begins. Major structures include twin bridges to take I-270 over Dahlia Street , a bridge to carry Quebec Street over I-270 and another two to take I-270 over I-70. Cost: $1.4 million for structures and $1.3 million for paving; Contractor: L.H. Kilgroe Construction Co. of Denver .

August 2, 1968 A three-mile segment of I-270 between Vasquez Boulevard and I-70 opens to traffic.

October 23, 1970 A two-mile segment of I-270 opens to traffic between I-80 (I-76) and US 85, adjoining the three-mile segment already in service. This segment completes the 5.2 mile circumferential route.

April 1993 Construction begins to extend I-270 from I-76 to the I-25/US 36 interchange. Phase I consists of extends I-76 from I-25 to Pecos Street, constructing an eastbound I-270 bridge over I-25 and reconstructing the east to northbound and east to southbound ramps. Cost: $11.4 million; Contractor: Centric/Jones Constructors; Complete: June 1994

June 1996 Cost: $12 million Contractor: Centric-Jones Co. Work: Constructed a total of five new bridges. Two of the bridges were for westbound I-270 over Washington Street and over I-25. Two bridges were for the exit ramp from northbound I-25 to 70 th Avenue . The final bridge connected northbound I-25 to westbound US 36. Duration: June 1996 through May 1998

July 1997 Cost: $9 million Contractor: SEMA Construction Co., Inc. Work: Constructed the I-270 westbound bridge over Clear Creek, widened the existing US 36 bridge over Broadway, realigned southbound I-25 to the westbound US 36 ramp, which included the construction of MSE walls. Duration: July 1997 through December 1998

June 1998 Cost: $19 million Contractor: Centric-Jones Co. Work: Completed the westbound I-270 extension between I-76 and US 36, built the Direct Connect HOV ramp between US 36 and I-25 and constructed a new alignment of northbound I-25 between I-76 and 84 th Avenue . Duration: June 1998 through June 2001

March 1999 Construction begins to replaces the I-270 bridges over Vasquez Blvd. Cost: $6.2 million; Contractor: PCL Civil Constructors; Completion: June 2000

October 1999 Cost: $8.5 million Contractor: Hamon Contractors, Inc. Work: Constructed eastbound I-270 from I-25 to York Street , including the new bridge structures at I-270 over Washington Street and I-270 over Clear Creek. This project was accelerated one year due to TRANs bonds. Duration: October 1999 through March 2002

June 2000 Cost: $21 million Contractor: Hamon Contractors, Inc. Work: Constructed seven structures at the I-270 and I-76 interchange, rebuilt ramp movements from westbound I-270 to eastbound and westbound I-76. This project was accelerated two years due to TRANs bonds. Duration: June 2000 through August 2003

March 2004 Cost: $21 million Contractor: SEMA Construction Co., Inc. Work: Constructed a flyover ramp from southbound I-25 to eastbound I-270 and reconstructed southbound I-25 in concrete between 84 th Avenue and I-76. This project would not have been constructed without TRANs bond monies. Duration: March 2004 through November 2005

Future Cost: $15 million Contractor: Yet to be determined Work: Constructs a flyover ramp from eastbound I-270 to eastbound I-76. Duration: On hold (depend on funding) - This is the final phase of this Strategic Transportation Project.

Back to Top

CDOT Personnel

C.W. “Chet” Andersen F.P. McNamara
Skip Hlad Jake Koenig
Moe Awaznezhad John Schwab
Daryl Miller Jim Powers

Back to Top


Colorado Department of Transportation
 

Main | Interstate 25 | Interstate 70 | Interstate 76 | Interstate 225 | Interstate 270 | Fun Facts | Contact Us

Email: Page Master regarding information on this page
Email: Web Master regarding website functionality

Last Modified:
Back to Top

 
State of Colorado