I-70B
West Study
Frequently Asked Questions
Q) What is an Environmental Assessment?
A) An Environmental Assessment
(EA) is being prepared pursuant to the National Environmental Policy
Act (NEPA) of 1969. The EA
is a comprehensive study that evaluates potential impacts – both
positive and negative – of the various alternatives under consideration. The
purpose of preparing an EA is to provide the community and decision
makers with key information on alternatives under consideration with
regard to their potential impacts to the built, natural, and social
environments of the study area. If there are no significant
impacts, a decision document called a Finding of No Significant Impact
(FONSI) is prepared. If the EA indicates there are significant
impacts, an Environmental Impact Statement (EIS) must be prepared.
Q) Why is this project needed?
A) I-70B currently exhibits poor traffic operations and higher
than average accident rates due to high congestion, frequent stops,
and access points. Even with the construction of Riverside Parkway,
I-70B traffic is expected to grow as population and employment grows
in the Grand Junction area. Due to these conditions, this project
has been identified as a high priority project by the the Colorado
Department of Transportation, the City of Grand Junction, and Mesa
County. Other needs identified as important for this project to address
includes providing effective
access to adjacent properties and addressing the limited and irregular bike,
pedestrian, and bus facilities along the corridor.
Q) How does this project relate to Riverside Parkway?
A) Riverside Parkway is being constructed
by the City of Grand Junction as part of a loop around the City core
to address both local and regional transportation needs. When completed,
Riverside Parkway will relieve some traffic congestion on I-70B and
provide an alternate route to I-70B. However, the uses serviced
by I-70B and Riverside Parkway are generally different as shown
on the attached figure "Use of I-70B Corridor". Forecasts
for year 2030 show that even with Riverside Parkway, I-70B traffic
will increase between 15% and 80% between 24 Road and 15th Street.
The I-70B project will address congestion caused by this traffic
growth, the higher than average rate of accidents in the corridor, property
access, and pedestrian/bicycle/bus needs of the corridor. See
a PDF map.
Q) When will the project be constructed?
A) The current project will first seek
to understand the problems and issues associated with I-70B, then
develop alternatives to address these issues. This process follows
the National Environmental Policy Act (NEPA) and includes an Environmental
Assessment (EA) where all alternatives are evaluated for potential
impacts resulting in the selection of a Preferred Alternative. This
result is expected in late 2007. Once this Preferred Alternative
has been approved, the Colorado Department of Transportation (CDOT)
can then begin design of those improvements that can be funded. CDOT
does not currently have funds allocated to fully construct the recommended
I-70B improvements, therefore, phasing of the improvements will
be necessary and dependent on current and future funding availability. Based
on the timing and complexity of the design process, construction
on the most critical portions of I-70B could begin in 2008
or 2009.
|