Project Information

Cost: $25.7 million

Contractor: Ames Construction, Inc.

Start Date: February 7, 2007

End Date: December 2008

Have questions or concerns?

Call the project hotline at 303-279-1935

To receive e-mail updates, contact Mindy Crane at mindy.crane@dot.state.co.us

 

 

I-70 and SH 58 Interchange Project

On February 7th, the Colorado Department of Transportation (CDOT) will begin an interchange improvement project at I-70 and State Highway 58 in order to improve access. The $25.7 million project will construct two new ramps and reconstruction or realign three other ramps:

A new ramp from eastbound I-70 to westbound SH 58 will be constructed

A new ramp from eastbound SH 58 to westbound I-70 will be constructed

The existing ramp from eastbound SH 58 to eastbound I-70 will be realigned and reconstructed without replacing the existing bridge

The existing ramp from westbound I-70 to westbound SH 58 will be realigned and reconstructed

The existing ramp from Youngfield Street to eastbound I-70 will be relocated approximately 1/4 mile to the south to accommodate a longer acceleration lane.

 

Colorado Department of Transportation  

Main | Schedule | Photos | Newsroom | Contact Us

Email: Page Master regarding information on this page
Email: Web Master regarding website functionality

Last Modified:
Back to Top

  State of Colorado