Chronology of Past Construction
November,
1991-
The first U.S. 285 widening project began.
October, 1993-
Phase I construction was completed. U.S. 285 between Parmalee Gulch Rd.
and Tiny Town was widened to four lanes and the Parmalee Gulch Flyover
was constructed.
$8.7 million
June, 1994-
Phase II construction began on U.S. 285 between Tiny Town and Goddard
Ranch Court.
November,
1996-
Phase II construction was completed. U.S. 285 was widened to four lanes
between Tiny Town and Goddard Ranch Ct. and a new intersection was built
at North Turkey Creek Rd.
$12.4 million
November 1998-
Started Phase IV of the continued widening of U.S. 285 to four lanes. Ames Construction, Inc. of Aurora, was the contractor of this $22 million project. During this phase of construction, U.S. 285 was widened from two lanes of asphalt pavement to a four lane concrete highway between Settlers Drive and Eagle Cliff Road. Project was completed in Spring 2002.
August, 1999-
Phase III widening was completed on U.S. 285 between Goddard
Ranch Ct. and Settlers Drive (Mountain High Chapel).
$11.7 million
|