Project Schedule

Work completed in July:

  1. Final epoxy striping.
  2. Final signing.
  3.  Roadway smoothness testing and associated grinding of bumps (if needed).
  4.  Clean up construction debris.
  5.  De-mobilize.

Work to be completed in August:

A.  Removal and replacement of approximately 500 tons of asphalt in the northbound right lane.  This is currently scheduled to be performed August 5th and 6th.

  1.  Roadway smoothness test and associated grinding of bump.

Traffic Control is a little different this year.  Construction hours for the northbound lanes are 8:30 am to 5:30 pm Monday through Thursday.  Construction hours for southbound traffic are 6:30 am to 3:30 pm Monday through Thursday.  On Fridays the starting hours remain the same as stated above but all lane closures will be picked up by 1:00 pm.

The Public Information Office hours are 8:30 am to 4:30 pm Monday through Thursday and 8:30 am to 1:00 pm on Fridays. The Public Information Officer for this project is Mark Straub. The Public Information Office phone number is 303-915-8568.

 
US 285 Main
Project Schedule
US 285 History
Press Releases
Project Photos
Future US 285 Projects
Contact Us

Colorado Department of Transportation   Main | Project Schedule | History | Press Releases | Newsletters
Photos | Future US 285 Projects | Contact Us

Email: Page Master regarding information on this page
Email: Web Master regarding website functionality

Last Modified:
Back to Top

  State of Colorado