 |
|
Project
Schedule
January 2007 to November 2007 (Phase I)
Completed
Project began with initial mobilization measures including signage
and barrier work. Daytime operations included utility relocates, bridge
and box culvert construction. Night-time operations included drainage
work, dirt hauling, and detour switchovers. Two right-turn lane closures
were in effect at the intersection for approximately 10 months to
accommodate the on-site detour which shifted all Powers Boulevard
traffic to the east side of the Powers corridor and the south side
of the Woodmen Road corridor. This facilitated the construction of
southbound Powers Boulevard and westbound Woodmen Road.
November 2007 to June 2008 (Phase II)
Completed Ahead of Schedule
Phase II consisted of Five Steps.
June 2008 to August 2008 (Phase III)
Phase III of the Powers Boulevard/Woodmen Road Interchange Project
will begin in early June 2008. It will start with a major traffic
shift placing all traffic in their respective new roadway alignments.
During this phase of construction, all traffic will be shifted to
the outsides of both Powers Boulevard and Woodmen Road segments.
The new northbound Powers Boulevard ramps for accessing both east
and westbound Woodmen Road will be open. Final improvements during
this phase will include completion of median work, removal of temporary
cross-over pavement, highway lighting, paving of final asphalt,
striping and seeding completion.
All impacts referenced above are subject to
change and conditional upon resources and weather.
|
|
|