Powers Blvd./Woodmen Rd. Interchange Project
Phase II of construction commenced in November
2007 and consisted of five steps. Step four is shown below. Phase
II was completed ahead of schedule early June 2008.
Step Four- Completed
Shifted northbound Powers
to new southbound alignment (over bridge).

Click here or on the image for printable .pdf file.